| Activity | Time | Done | Upladed to e-twinning |
1. | Project team meeting, evaluation of 1 project year, activities and agreements about 2 project year | Sept 2019 | done | |
2. | Renewal of project page on institution webpage | Oct 2019 | done | |
3. | Creating webmagazine about project 1. year activities | Nov 2019 | | |
4. | 3. smartweek with children (if not done in june or august) | sept 2019 | done | |
5. | Weather tracking in autumn | Oct 2019 | | |
6. | Summaries about Smartweek | Dec, 2019 | done | |
7. | Creating materials to introduce France | Oct 2019 | done | |
8. | Project team meetings – preparations for parctical workshop conducted in 3. training event. | Oct 2019 | done | |
9. | Renewal of project webpage | Dec 2019 | | |
10. | 3. training event in France, presentations for workshops | Nov 2019 | done | |
11. | Summaries about 3. training event | Nov 2019 | done | |
12. | Introduction of France in partner institutions for children | Dec 2019 | done | |
13. | Training inside every institution for all teachers – topics handled on 3. training event | Dec 2019 | done | |
14. | 4. Smartweek with children | Jan 2020 | done | |
15. | Summaries about Smartweek | Jan 2020 | done | |
16. | Summaries of weather tracking – 4 seasons in my country | Jan, Feb 2020 | done | |
17. | Project team meetings – preparations for parctical workshop conducted in 4. training event. | Feb 2020 | done | |
18. | Creating materials to introduce Spain | Jan, Feb 2020 | done | |
19. | 4. training event in Spain, presentations for workshops | March 2020 | Activity was cancelled because covid-19 | |
20. | Summaries about 4. training event | March 2020 | Activity was cancelled because covid-19 | |
21. | Internet security seminar | March, april 2020 | Activity was cancelled because covid-19 | |
22. | Conducting post project questionnaires with children, teachers, parents | March 2020 | Activity was cancelled because covid-19 | |
23. | Renewal of institution curriculum | March 2020 | Activity was cancelled because covid-19 | |
24. | Introduction of Spain in partner institutions for children | April 2020 | Activity was cancelled because covid-19 | |
25. | Training inside every institution for all teachers – topics handled on 4. training event | April 2020 | Activity was cancelled because covid-19 | |
26. | Summaries about questionnaires | April 2020 | Activity was cancelled because covid-19 | |
27. | 5. Smartweek week with children | April, may 2020 | Activity was cancelled because covid-19 | |
28. | Dissemination event in every partner institution | April 2020 | Activity was cancelled because covid-19 | |
29. | Summaries about Smartweek | May 2020 | Activity was cancelled because covid-19 | |
30. | Project team meetings – preparations for parctical workshop conducted in 5. training event. | May 2020 | Activity was cancelled because covid-19 | |
31. | Creating materials to introduce Greece | Apr, may 2020 | Activity was cancelled because covid-19 | |
31. | 5. training event in Greece, presentations for workshops | May 2020 | Activity was cancelled because covid-19 | |
33. | Summaries about 5. training event | June 2020 | Activity was cancelled because covid-19 | |
34. | Training inside every institution for all teachers – topics handled on 5. training event | June, 2020 | Activity was cancelled because covid-19 | |
35. | Project summaries, evaluation and comparison of questionniares results - outcomes | May, June 2020 | Activity was cancelled because covid-19 | |
36. | Finishing e-twinning | May, june 2020 | Activity was cancelled because covid-19 | |
37. | Finishing project webpage | May, june 2020 | Activity was cancelled because covid-19 | |
28. | Learning activities with children using different smart and ICT equipment and educational robots through out the year. | Sept 2019 – may 2020 | Activity was cancelled because covid-19 | |
39. | Project dissemination report | June, 2020 | done | |
40. | Introduction of Greece in partner institutions for children | June 2020 | Activity was cancelled because covid-19 | |
41. | Project extra activities report | June, 2020 | Activity was cancelled because covid-19 | |
42. | Project dissemination materials | June 2020 | Activity was cancelled because covid-19 | |
43. | Finishing mobility tool | June 2020 | Activity was cancelled because covid-19 | |
44. | Finishing project outcomes platform | June 2020 | done | |
45. | Final reports | June, august 2020 | report in february 2021 | |